Site Preparation

  1. Remove sharp objects: Clear stones, debris, and protrusions
  2. Level the surface: Use sand blinding if necessary
  3. Install service ducts: Position before membrane installation
  4. Check moisture content: Concrete slab must be dry

Membrane Installation

Laying the Membrane

  • Unroll membrane with printed side up
  • Allow 300mm upstand at walls and foundations
  • Ensure minimum 300mm overlap between sheets
  • Avoid stretching or wrinkling the membrane

Joint Sealing

Two methods are commonly used:

Tape Method

  • Clean membrane surface at joint
  • Apply manufacturer's jointing tape (minimum 100mm wide)
  • Press firmly to ensure full adhesion
  • Roll with seam roller for uniform pressure

Welding Method

  • Use hot air welder at specified temperature
  • Maintain consistent speed (typically 2-3 m/min)
  • Test weld strength before proceeding
  • Allow weld to cool before testing

Penetration Details

  • Use pre-formed pipe collars or site-fabricated boots
  • Seal with compatible tape or weld
  • Test all penetrations for gas tightness

Testing & Verification

  • Visual inspection: Check all joints and penetrations
  • Air pressure test: Pressurize membrane and monitor decay
  • Documentation: Record test results and installation details

Protection Layer

  • Install protection board before concrete pour
  • Use minimum 50mm sand blinding for mechanical protection
  • Pour concrete within 7 days of membrane installation